Have you found yourself in a situation where you require documents for both professional or personal purposes nearly every day.
There are numerous legal document templates available online, but locating ones you can trust isn’t straightforward.
US Legal Forms provides thousands of document templates, such as the Florida Contractor's Final Punch List, designed to satisfy state and federal requirements.
Once you and the contractor agree on what belongs on the punch list, ask the contractor for a time commitment (one to two weeks?) to complete the work. At that time, you make a final inspection and, assuming everything is OK, make the final payment.
Final Completion and Final Payment.. 1.1"Final Completion" is the point at which all Work on the Project, including all punch list and Close-out Requirements, have been completed by the Contractor in strict compliance with the Contract requirements and the Contractor is ready to receive its Final Payment.
A punch list is a document that lists final work items remaining before a construction project is considered complete. All work that does not conform to the specifications in the construction contract should be included in the punch list.
Most contracts define substantial completion as the date upon which the work is sufficiently complete so as to allow the owner to occupy and fully use the project for its intended purposes. Punch list items will not prevent substantial completion.
A punch list is a document prepared near the end of a construction project that lists issues in the home that don't conform to the contract. Contractors must then complete the work before final payment.
Final Punch List means the list of items and schedule for completion of the Project required to be completed by Contractor following the Substantial Completion Date.
In regards to construction today, the Business Dictionary defines a punch list as, Listing of items requiring immediate attention and as a Document listing work that does not conform to contract specifications, usually attached to the certificate of substantial completion.
A punch list is a document prepared during key milestones or near the end of a construction project listing work that does not conform to contract specifications that the general contractor must complete prior to final payment.
The term punch out work refers to remaining action items that must be completed before a project officially ends. This term also describes the process of completing a punch list and indicating approximate timing of remaining tasks. Typically, the punch out is the last aspect of a construction project.