As a general rule, if the owner hired whoever drafted the construction plans, or if whoever drafted the faulty plans is an employee or agent of the owner, it is the owner who will be liable for defective plans.
The major difference between lump sum and EPC is that, in EPC the contractor has the responsibility of design and construction. b. Where as in lump sum contract the design and drawings are prepared by the technical team of the owner.