Summary Motion to Remove Invalid or Unenforceable Lien. (a) In a suit brought to foreclose a lien or to declare a claim or lien invalid or unenforceable, a party objecting to the validity or enforceability of the claim or lien may file a motion to remove the claim or lien.
On residential projects, the deadline to file a Texas mechanics lien is the 15th day of the 3rd month after the month the contract was completed, terminated, or abandoned.
Constitutional and Statutory Mechanic's Liens Texas has two types of mechanic's liens—constitutional and statutory. All Texas mechanic's liens have their source in Article XVI, Section 37 of the state constitution, which provides for the lien and instructs the legislature to provide for its enforcement.
File the lien: A construction lien is typically filed with the county clerk in which the project is located. The paperwork and filing requirements vary by state, but will usually involve listing the work performed, the unpaid amount(s) at issue, as well as attaching copies of contracts and any required notices.
Creditors know that putting a lien on your property is a cheap and almost guaranteed way of collecting the debt they're owed. In some states, contractors and subcontractors must notify the property owner before filing a lien, but in other states property liens can be filed without any notice to the owner.
To file a lien claim, you will need: The amount owed for each month you performed the work that remains unpaid. A brief description of the work you performed. The original contractor's name (general contractor) and mailing address (only if you are a subcontractor or sub-subcontractor).
Generally, Texas imposes no specific requirement that a contract be in writing to be eligible for lien protection. However, prime contractors on homestead properties must have a written contract with the property owner to be able to secure lien rights on the project.
Except as permitted below for the filing of liens for Contractual Retainage only, a claimant must file its lien affidavit not later than the 30th day after the earliest of the completion, termination, or abandonment of the original contract.
Contractors can file a lien on a property without a written contract in most cases. However, if the project in question is on a residential homestead property, a written contract must be filed in the local property records and is required to enforce mechanic's lien filing rights.