Contracts 'with quantities' are priced on the basis of drawings and firm bills of quantities. 'Without quantities' means a contract priced on the basis of drawings and usually another document, such as a specification or work schedules.
The JCT Standard Building Contract is designed for large or complex construction projects where detailed contract provisions are needed. Standard Building Contracts are suitable for projects procured via the traditional or conventional method.
The JCT Measured Term Contract is designed for use by employers who have a regular flow of maintenance, minor works and improvements projects that they would like to be carried out by a single contractor over a specified period of time.
JCT contracts are known for being highly prescriptive. Although the standardised format may provide clarity, it can also limit flexibility. Each JCT contract is structured around a specific set of terms and clauses, which may not suit every project's unique needs or challenges.
Usually a JCT contract is made between an 'employer' (the client) and the 'contractor' (the construction team) to make the process as seamless as possible. It's a document containing the obligations of everyone involved, the agreed costs and timelines, terms and conditions, and the specifications of the project.
What is a standard form contract? While many contracts are entirely purpose made, standard form contracts consist of standardised, pre-written terms and conditions. Because standard form contracts are familiar to people in an industry, they often function effectively without the need for much negotiation.
A standard form contract (sometimes referred to as a contract of adhesion, a leonine contract, a take-it-or-leave-it contract, or a boilerplate contract) is a contract between two parties, where the terms and conditions of the contract are set by one of the parties, and the other party has little or no ability to ...
Clause 4.11 – In the event of non-payment or non-compliance with the above-mentioned Clauses, the Contractor has the right to suspend works and the process for doing so is explained in this Clause.
The JCT Standard Building Contract is designed for large or complex construction projects where detailed contract provisions are needed. Standard Building Contracts are suitable for projects procured via the traditional or conventional method.
The employer must provide drawings together with a description of works, and either a specification or work schedules at tender stage. The project is generally not complex enough to require bills of quantities.