Drafting paperwork, such as the Fairfax Easement and Right of Way (For Electrical Transmission Lines - Long Form), to handle your legal affairs is a challenging and lengthy endeavor.
Numerous circumstances necessitate the engagement of a lawyer, making this task quite costly.
However, you can take charge of your legal matters and address them independently.
Here’s what you should do before obtaining the Fairfax Easement and Right of Way (For Electrical Transmission Lines - Long Form): Ensure your document is tailored to your state/county as the regulations for drafting legal documents can vary from state to state.
Our transmission lines are generally built on easements over the land. An easement gives us the legal right to access land to carry out work to build, operate and maintain our transmission network. The easement is registered on the property title and the landholder retains ownership and responsibility for the land.
The right of way is a strip of land where the transmission line is constructed, erected, operated and maintain. The transmission line is kept in the centre of right of way ( ROW ). The right of way clears all trees, structure and construction which interference the power lines.
Easement agreements impact every landowner and the public in a given location for the lifetime of the deal. Landowners retain the right of use to the land through these agreements, as long it doesn't interfere with the utility company's immediate access.
Transmission overhead powerlines range in voltage from 132kV up to 500kV. They are installed on towers or steel poles. Transmission lines are typically installed in easements and permission is required before any work can be undertaken on the easement.
Homeowners and Easements All types of utility companies are granted easements on the lands over or under which their lines run. Your electric power company, for example, usually has an easement to use the portion of your land on which its towers and lines sit. However, an easement holder doesn't own the land.
The size of such easement shall be deemed to be the greater of the actual occupancy of the easement in the incumbent utility's usual course of business or 7.5 feet on each side of the installed facilities' center-line. "Public utility" has the same meaning as provided in § 56-265.1.
A major goal of overhead power line design is to maintain adequate clearance between energized conductors and the ground so as to prevent dangerous contact with the line, and to provide reliable support for the conductors, resilience to storms, ice loads, earthquakes and other potential damage causes.
Towers and substations have "High Voltage" warning signs posted on them because of their extreme danger. Only qualified personnel may access these structures and facilities. Do not attempt entry into any substation and do not touch any electrical tower.
You must NOT place obstructions in the easement within 5 metres of a power line, transformer, pole, equipment or support wire, or within 10 metres of a steel power line structure.
Although right of way widths can vary, generally: Most TVA transmission line rights of way are 75 to 200 feet wide. Rights of way for multiple transmission lines are generally wider. 500kV lines commonly use a 175 or 200-foot right of way.