Clause 4.11 – In the event of non-payment or non-compliance with the above-mentioned Clauses, the Contractor has the right to suspend works and the process for doing so is explained in this Clause.
The Standard JCT Contract is drafted to suit larger works, or works of a complex nature that involve a high degree of building services or specialist work and its drafting to include provisions allowing: for the contractor to design discrete parts of the works.
Clause 4.7. 2 4.7. 2 The sum due as an Interim Payment shall be an amount equal to the Gross Valuation under clause 4.13 where Alternative A applies, or clause 4.14 where Alternative B applies, in either case less the aggregate of: 4.7.
So, if you ever come across someone referring to a 'JCT contract', it is typically about a standard building contract. These contracts are usually between an 'employer' and a 'contractor' to facilitate a building works project. They set out all of the relevant terms and conditions, including: Obligations of the parties.
The term 'without quantities' refers to a construction contract or tender documents that do not include specific measured quantities of the items of work identified by the drawings and specifications. It can be used on projects where it is not possible to prepare a bill of quantities (BOQ) at the time of tendering.
The employer must provide drawings together with a description of works, and either a specification or work schedules at tender stage. The project is generally not complex enough to require bills of quantities.
4.21. 1 The Contractor shall notify the Architect/Contract Administrator as soon as the likely effect of a Relevant Matter on regular progress or the likely nature and extent of any loss and/or expense arising from a deferment of possession becomes (or should have become) reasonably apparent to him.
Saves time: by streamlining and simplifying the process. Comprehensive: JCT contracts are thorough documents, covering most potential issues and reducing the risk for the employer should their contractor's quality of work be inadequate or not delivered to the agreed time.
Below, we'll go into more detail about each one-line aspect that could mean that your organization's contract process isn't working properly: No central storage location/no contract reporting. Friction between teams. Overloaded legal department. Long and opaque contract cycles. Lack of overview and missed contract deadlines.
Contracts 'with quantities' are priced on the basis of drawings and firm bills of quantities. 'Without quantities' means a contract priced on the basis of drawings and usually another document, such as a specification or work schedules.