4.21. 1 The Contractor shall notify the Architect/Contract Administrator as soon as the likely effect of a Relevant Matter on regular progress or the likely nature and extent of any loss and/or expense arising from a deferment of possession becomes (or should have become) reasonably apparent to him.
The term 'without quantities' refers to a construction contract or tender documents that do not include specific measured quantities of the items of work identified by the drawings and specifications. It can be used on projects where it is not possible to prepare a bill of quantities (BOQ) at the time of tendering.
So, if you ever come across someone referring to a 'JCT contract', it is typically about a standard building contract. These contracts are usually between an 'employer' and a 'contractor' to facilitate a building works project. They set out all of the relevant terms and conditions, including: Obligations of the parties.
The employer must provide drawings together with a description of works, and either a specification or work schedules at tender stage. The project is generally not complex enough to require bills of quantities.
JCT contracts are known for being highly prescriptive. Although the standardised format may provide clarity, it can also limit flexibility. Each JCT contract is structured around a specific set of terms and clauses, which may not suit every project's unique needs or challenges.
Clause 4.11 – In the event of non-payment or non-compliance with the above-mentioned Clauses, the Contractor has the right to suspend works and the process for doing so is explained in this Clause.
Clause 4.7. 2 4.7. 2 The sum due as an Interim Payment shall be an amount equal to the Gross Valuation under clause 4.13 where Alternative A applies, or clause 4.14 where Alternative B applies, in either case less the aggregate of: 4.7.
Saves time: by streamlining and simplifying the process. Comprehensive: JCT contracts are thorough documents, covering most potential issues and reducing the risk for the employer should their contractor's quality of work be inadequate or not delivered to the agreed time.
A more important problem with the theory is that it is easy to exclude the poor, the dispossessed, the homeless, and the uneducated. These members of a society may not know the rules intended to govern member's behavior and do not benefit from the social contract.
JCT contracts don't specify remedies for common issues. They rely on existing case law precedents to find a resolution. This can be complex and time-consuming, and seriously impact project timelines.