Submittals will be accepted using the Plans Status & Application Portal and/or in person. For in person submittals, documents will be converted into electronic format. The plan review will be completed electronically by multiple departments simultaneously, thus expediting the permitting process.
If you have any questions, you can view the Building Department Directory, call (305) 416-1100, or email eplanbuilding@miamigov The Building Department is located at Miami Riverside Center - 444 SW 2nd Ave, 4th floor, Miami, FL 33130.
NOTE: For a Building permit application it usually takes 14 business days for the first cycle of review to be completed. For a Special permit application, it usually takes 35 business days for the first cycle of review to be completed.
Follow these steps to upload your documents: Complete the online Permit Application/Document Submission form. To add/upload documents, click on the “Add Files…” button. Ensure you have selected all the files you intend to upload. Select the “Submit” button and wait for the upload to complete.
Add/Update Your Building Professional Once in iBuild, select 'Manage Application' and select Add/Update Contractor (GC, subs like electricians, etc.). You will need your contractor's company + qualifier license number, as they have to be registered to do work in the City of Miami.
By dialing 311 or 305-468-5900 (outside Miami-Dade County), you can receive personalized customer service in English, Spanish or Haitian Creole. The 311 Contact Center is open Monday through Friday from 7 a.m. to 7 p.m. and Saturday from 8 a.m. to 5 p.m., while closed on Sundays and holidays.
NOTE: For a Building permit application it usually takes 14 business days for the first cycle of review to be completed. For a Special permit application, it usually takes 35 business days for the first cycle of review to be completed.
To cancel a permit, submit a completed permit cancellation form to RERPERCAN@miamidade. CANCELLATIONS WHERE NO WORK HAS BEEN PERFORMED: To cancel a permit where the work will not be taking place, the following must be submitted.
Permits are needed for a variety of construction projects, from home additions to swimming pools and spas, sheds, pergolas and gazebos, fences, windows, doors and more.
Schedule of Fees ApplicationFee Campus Master Plan $1,135 + $8/100 sq. ft. Campus Master Plan Amendment $541 Certificate of Use $250 Certificate of Use, Renewal $25057 more rows