Exhaustive, of examples of force majeure events. Force majeure events generally can be divided into two basic groups: natural events and political events. These may include earthquakes, floods, fire, plague, Acts of God (as defined in the contract or in applicable law) and other natural disasters.
Templates. “Force Majeure: Neither party shall be liable for any failure or delay in the performance of any obligations under this Agreement, except for the obligation to make payments, if such failure or delay is caused by a Force Majeure event.
Force majeure clause samples 10.2 The Party affected by Force Majeure shall not assume any liability under this Agreement. Section 15.12 Force Majeure. 6.4 If the agreement cannot be performed due to force majeure, the responsibility shall be exempted in part or in whole ing to the influence of force majeure.
Typically, the clause will define the specific events or circumstances that qualify as force majeure, providing a non-exhaustive list of examples. These examples often encompass natural disasters, acts of God, riots, embargoes, or any other events that are considered extraordinary and beyond the control of the parties.
12.1 If at any time during the course of the MoU it becomes impossible for either Party to perform any or all of their obligations for reasons of Force Majeure which shall be defined as "acts of nature, invasion or acts of God or events beyond the reasonable control of either Party, any act of war, invasion, armed ...
Here is an example of a force majeure clause template: Force Majeure: Neither party shall be liable for any failure or delay in performance under this Agreement due to causes beyond its reasonable control, including but not limited to acts of God, government restrictions, wars, insurrections, or natural disasters.
The company declared force majeure on some contracts after heavy rains at the site of its mines. If any force majeure event continues for thirty days or more, either party may terminate this Agreement immediately by written notice.
Commonly referred to as “acts of God”, force majeure events are unforeseeable, exceptional or out with the control of contracting parties. Examples include natural disaster, terrorism, industrial strike action, fire and pandemic/epidemic events such as Covid-19.
Force majeure clauses typically identify such events as excusable delays, allowing the contractor a time extension. However, these clauses are typically silent as to responsibility for delay costs and additional direct costs that result from the force majeure event.
Either Party shall be excused from performance and shall not be in default in respect of any obligation hereunder to the extent that the failure to perform such obligation is due to a Natural Force Majeure Event.