The contract should describe, in detail, the products to be used and how the work will be performed, i.e., size, color, who will be doing what work, amounts of materials provided, manufacturer model number, etc. There must be a detailed, written payment schedule in the contract.
Final payments from the owner to the prime contractor become due within 45 days after the completion of the entire project. Upon receipt of payment from the owner, the prime contractor needs to make payment to their subs and suppliers within 10 days. The same deadline applies to all other payments down the chain.
Initial Payment: $1,000 or 10% (whichever is less) Demo and Prep Work Completion: 20%